Checking the Building Control Records

A missing completion certificate does not necessarily mean the work was carried out without approval. An application may exist but remain unfinished, or a certificate may have been issued and lost. We review the available drawings, decisions and inspection records to establish what was done and which parts of the process remain outstanding.

That distinction determines the next step: obtaining a copy of an existing certificate, resolving outstanding matters under an earlier application, or considering Building Regulations regularisation. We also assess any concerns about the construction itself, whether the issue has arisen during a sale, a remortgage or your own review of the property.

Roof timbers and loft floor visible during inspection of an existing house
Existing roof structure & accessible supports
Part-open glazed stable-style door showing the existing opening
Openings, fittings & construction details

Inspecting the Existing Construction

Unauthorised Loft Conversions

An unauthorised loft conversion needs to be considered as part of the house, including how the altered roof and new floor are supported and how occupants would escape in a fire. We inspect the accessible construction, stairs and accommodation, considering insulation, ventilation and other relevant details alongside the available records.

We compare what is built with any earlier drawings and identify defects or departures that need attention. The assessment explains which parts can be established from inspection and records, and where further investigation is needed before repairs or alterations can be designed.

Joint Structural Inspections

Where structural concerns need investigating alongside the building’s layout and fire precautions, we can inspect jointly with our consulting Chartered Structural Engineer, Stephen D’Aulby. This brings the building assessment and engineering advice together, particularly for altered roofs, new floors, removed walls and beams supporting earlier alterations.

The engineering assessment considers the supports, connections and loads, while our wider inspection addresses the construction and arrangement of the accommodation. We explain whether further measurements, calculations or investigations are needed to complete the assessment.

Opening-Up & Further Investigation

Plasterboard, floor finishes and roof linings can conceal joists, beam bearings, insulation and fire protection. We use the inspection findings and available construction records to identify the particular areas that need exposing and the information each opening should reveal.

Before opening-up takes place, agree the locations, the owner’s permission, who will carry out the work and how the finishes will be made good. The findings can then be inspected and recorded before the construction is covered again, including any inspection required by Building Control.

What Our Assessment Covers

Our report records the construction inspected, the documents reviewed and the defects or unresolved questions affecting the work. It explains the findings and recommends the next steps, which may include structural calculations, further inspection, remedial design or a Building Control application.

You can use the report to understand what needs attention and discuss the technical position with your advisers. A completion or regularisation certificate is issued through the relevant Building Control process; our report supplies technical evidence and advice to support that process.

Remedial Design & the Building Control Process

Drawings & Remedial Design

Where alterations are needed, we can prepare architectural drawings and coordinate structural details showing how the defects should be addressed. A loft conversion might need additional support, changes to the staircase or improvements to fire protection, with the design based on what the investigation establishes.

The drawings distinguish the existing construction from the proposed remedial work, giving Building Control the information to assess and contractors a basis for pricing. A specification can add the materials and workmanship requirements where more detailed instructions are needed.

Applying for Building Regulations Regularisation

For eligible unauthorised building work carried out on or after 11 November 1985, the owner can apply retrospectively for a regularisation certificate. Ordinary house alterations are dealt with by local authority Building Control, which assesses the work against the Building Regulations requirements applicable when it was carried out.

We can prepare drawings of the existing work and any proposed alterations, supported by inspection findings and structural information. The authority may require construction to be exposed, tests carried out or defects corrected before it can decide whether the relevant requirements have been met and issue a certificate.

Regularisation addresses Building Regulations, so any missing Planning Permission or Listed Building Consent must be considered separately. Higher-risk building work follows a separate Building Safety Regulator procedure, which must be checked at the outset.

Lender, Valuer & Solicitor Enquiries

If a lender, mortgage valuer or solicitor has requested a report, send us their exact wording with the property details. We can then establish the inspection and engineering input needed to answer those questions, and explain what information you will receive before you instruct us.

A request about the condition of a loft conversion may need a different response from a request for a Building Regulations certificate. We clarify what our assessment can establish before you book, so your advisers can check it against the lender’s requirements.

Frequently Asked Questions

What if an application exists but there is no completion certificate?

The existing application and inspection history should be reviewed first. There may be outstanding inspections, certificates or construction details to resolve, or a copy of an issued certificate may be available. Regularisation is not automatically the right route simply because the owner cannot produce the paperwork.

Can work carried out before November 1985 be regularised?

The regularisation procedure applies to eligible unauthorised work carried out on or after 11 November 1985. Earlier work can still be inspected for defects and structural concerns, but that assessment does not produce a regularisation certificate. We review the available dates and records before advising on the technical work needed.

Will the work have to meet today’s Building Regulations?

Earlier work is generally assessed against the Building Regulations requirements that applied when it was carried out, while new alterations may need to meet current standards; we identify which requirements apply to each part.

How long does regularisation take?

It depends on the records available and whether opening-up, calculations or remedial work are needed before the authority can decide, so raise the issue early if a sale or remortgage has a deadline.

Can construction photographs reduce opening-up?

Clear photographs showing the location and sequence of the work can help identify concealed construction, especially when they can be matched to drawings or calculations. We review them before recommending exposure, although Building Control may still need to inspect particular details or request further evidence.

What if indemnity insurance has been suggested?

Ask your solicitor to review the proposed policy and the effect of contacting Building Control before anyone makes enquiries. The terms determine what is covered, and insurance does not establish whether the construction is sound or compliant. Our inspection addresses the condition and technical questions affecting the work.