Start with the Notice & Proposed Work

If your neighbour has served a Party Wall notice, send us the full notice, drawings and the date you received them. We identify the work being notified, the relevant response deadline and any information needed to understand its effect on your property.

This may include excavation depths, foundations, alterations to a shared wall, temporary support and proposed access. Raise particular concerns early, such as existing cracks, a vulnerable extension or work close to your foundations.

Your Choices after a Party Wall Notice

For Party Structure and excavation notices, written consent is normally needed within 14 days to avoid a statutory dispute arising. The Line of Junction provisions work differently: a wall astride the boundary needs consent; without it, the new wall must be on the building owner’s land.

Consent to the Work

If you understand the proposals and are content to proceed, you can give written consent. A dated Schedule of Condition can still provide a useful record before work begins. Consent does not remove your rights under the Act.

Appoint Your Own Surveyor

If a dispute arises, you may appoint a surveyor to deal with the matters covered by the Act. Your surveyor considers the proposals with the building owner’s surveyor and works towards an Award.

Use an Agreed Surveyor

Both owners can appoint one Agreed Surveyor if they are comfortable with that arrangement. The surveyor acts impartially for the statutory process and is not either owner’s advocate.

Close view of existing brickwork, render and a window opening
Recording existing walls & finishes
Existing conservatory beside a boundary wall with a narrow paved space
Understanding neighbouring construction

Reviewing the Work & Recording Your Property

Understanding the Construction

We review the notified work and relevant drawings, considering how excavation, support, cutting into shared structures or changes at the boundary may affect your property.

Where details are incomplete, we seek the information needed to address the Party Wall matters. Structural calculations or specialist advice may be needed for more complex proposals.

A Schedule of Condition before Work

A dated written and photographic record documents the accessible areas likely to be affected. It records existing cracks, finishes, damage and earlier repairs so there is evidence to compare with the condition after construction.

Tell us about previous movement, leaks or repairs, and provide older photographs where available. The inspection records relevant condition; it is not a general Building Survey of your home.

An Independent Statutory Role

Although you appoint us, a Party Wall surveyor must act impartially within the Act. The process addresses the notified work, protection and relevant disputes; it does not determine a Planning objection or a separate boundary ownership dispute.

What the Party Wall Award Covers

Where an Award is required, it records how the relevant work may proceed and the safeguards appropriate to it. Depending on the proposals, it may address:

  • The drawings, methods and sequence of notified work
  • Temporary support and protection for adjoining structures
  • Working arrangements, access and relevant notices
  • The Schedule of Condition and further information required
  • Making good damage, compensation and surveyors’ costs

An Award deals with matters within the Act. Planning Permission, Building Regulations and other private rights remain separate.

During the Work: Damage & Protection

If You Notice Damage

Tell the surveyor promptly and take dated photographs. The evidence can be compared with the pre-work schedule and construction sequence to assess whether the notified work caused the damage.

The building owner is responsible for making good damage caused by work under the Act, or paying compensation instead where the adjoining owner requests it. The appropriate response is addressed through the statutory process.

Security for Expenses

In appropriate circumstances, an adjoining owner can request security for expenses before work begins. This is a specific provision of the Act, with the need, amount and arrangements considered for the proposed work.

Raise this early so it can be addressed by agreement or Award before construction starts.

Who Pays for the Adjoining Owner’s Surveyor?

For work undertaken solely for the building owner’s benefit, that owner normally pays the reasonable surveyors’ fees. The statutory allocation can differ where work benefits both owners or concerns shared repairs.

We explain the likely fee arrangements before appointment. Separate advice outside the Party Wall appointment is identified and agreed with you beforehand.

If Work Has Started without a Notice

Contact us promptly with photographs, the address and details of the work. We first consider whether it falls within the Act and what stage it has reached. Record the current condition of your property and any developing damage.

The absence of a notice cannot simply be remedied by a retrospective Party Wall Award. If urgent legal action is being considered, a solicitor can advise on the available remedies, including whether an injunction is appropriate.

Read Our Party Wall Guide

Frequently Asked Questions

Do I lose my rights if I consent?

Consenting confirms that you agree to the notified work at that point; it does not remove your rights under the Act. If a dispute later arises over damage or another matter covered by the Act, the surveyor procedure remains available.

Can I stop the proposed work?

The Act does not give you a general veto over work your neighbour has a right to carry out. Where an Award is required, however, the work it covers must wait until the Award has been served and the applicable notice periods and conditions have been met. Separate Planning or boundary issues may need other advice.

Do I have to allow access to my property?

The Act can require access for work or inspections authorised by it, rather than unrestricted access for the whole project. The Building Owner normally needs to give both the owner and occupier at least 14 days’ notice. In an emergency, as much notice as reasonably practicable is required; we can explain how the proposed access relates to the notified work.

What if I do not appoint a surveyor?

Once a dispute has arisen, the Building Owner can serve a written request requiring you to appoint a surveyor. If you have not appointed within ten days, beginning with the day that request is served, they can appoint a separate surveyor on your behalf under section 10(4). Responding allows you to choose your own surveyor or agree a joint appointment.

What if my neighbour changes the plans?

Send the revised drawings or details of the change to your appointed surveyor. They can check whether the work remains covered by the notices and Award, or whether a further Award or fresh notice is needed before the altered work proceeds.

Can I challenge the Party Wall Award?

Either owner may appeal to the county court within 14 days, beginning with the day the Award is served on them. Take legal advice promptly if you intend to challenge it, as discussing concerns with the surveyors does not extend that deadline.