Preparing Party Wall Notices

We review the drawings and ownership information to identify which Party Wall notices are needed and who must receive them. This can include freeholders and qualifying leaseholders, so the person living next door may not be the only owner who needs notice.

The notices describe the proposed work and intended start date, with the plans and details required by the Act. One project may need more than one type of notice, depending on the work involved.

Line of Junction Notice

A section 1 notice is used for certain new walls at the boundary and requires at least one month’s notice. A new wall astride the boundary needs the adjoining owner’s written consent. Without it, the wall must be built wholly on the Building Owner’s land after the notice period.

Party Structure Notice

A section 3 notice covers work to existing party walls and structures under section 2, with at least two months’ notice. Typical examples include inserting beam bearings for a loft conversion, removing a chimney breast, raising a Party Wall and rebuilding or repairing a shared structure.

Notice of Adjacent Excavation

A section 6 notice requires at least one month’s notice where the excavation meets either of these tests:

  • Within three metres: the excavation extends below the bottom of the neighbour’s foundations.
  • Within six metres: the excavation meets a plane drawn downwards at 45 degrees from the bottom of the neighbour’s foundations at the outside face of their wall.

These distances are measured from the neighbouring building or structure, rather than the boundary. Plans and sections must show the excavation’s position and depth and the position of any proposed building. The notice also states whether the neighbouring foundations will be underpinned, strengthened or otherwise safeguarded.

Responding to a Party Wall Notice

For Party Structure and excavation notices, the adjoining owner can consent in writing or dissent. If written consent is not given within 14 days of service, a dispute is treated as having arisen under the Act, even if the owners are on good terms.

The owners then appoint separate Party Wall surveyors or agree in writing to use one Agreed Surveyor. The surveyors settle the matters in dispute through a Party Wall Award, setting out the work and the protections needed for the adjoining property.

Line of Junction notices follow a different procedure: a lack of response does not create the same automatic dispute, although an actual disagreement about work under section 1 can still require surveyors to resolve it.

Existing chimney breast, painted walls and ceiling cornice
Recording the existing wall, ceiling and fireplace finishes before work.

Schedule of Condition

Before work begins, we inspect the parts of the adjoining property that could be affected and record existing cracks, finishes and other visible defects in writing and photographs. Descriptions identify the rooms and building features concerned, and we note any areas we cannot inspect.

The Schedule of Condition gives both owners a dated record to refer to if damage is reported later. Comparing it with the condition after the work and other evidence helps establish whether the construction caused a new defect or made an existing problem worse.

What the Party Wall Award Covers

A Party Wall Award is the appointed surveyors’ decision on matters in dispute under the Act. It identifies the work authorised and sets out how it is to be carried out, normally referring to the drawings and Schedule of Condition. Depending on the project, it can cover:

  • construction methods, sequence and working hours
  • temporary support, weatherproofing and other protection
  • access needed for the work and inspections
  • making good damage or payment in lieu
  • security for expenses where required
  • reasonable surveyor fees and other relevant costs.

Planning, Building Regulations & Boundaries

Planning Permission and Building Regulations approval remain separate requirements, and an Award does not settle ownership or determine a disputed boundary. Access and foundation rights depend on the particular provisions of the Act, so they must be checked against the proposed work rather than assumed from the existence of an Award.

When Can Work Start?

Where a Party Wall Award is needed, it must be served before the work it covers begins. The relevant notice period must also have expired unless the owners have agreed an earlier start, and any conditions that apply before work begins must be met.

We review the construction programme alongside the notices and drawings so the contractor knows which operations need to wait. Work elsewhere on the project may be able to proceed, provided it does not involve or depend on the work still awaiting completion of the Party Wall procedure.

Damage, Security & Costs

Damage & Making Good

If damage appears, tell the surveyor promptly and take dated photographs before repairs obscure it. We compare the damage with the Schedule of Condition and other evidence to assess whether it was caused or worsened by the work.

Where the work causes damage covered by the Act, the Building Owner is responsible for putting it right. If the owners disagree about the repairs or payment in lieu, the surveyors can settle the matter through a further Award.

Security for Expenses

Before work begins, an adjoining owner can serve notice requiring security for expenses. This provides financial protection if work is left unfinished at a stage that puts their property at risk, such as an incomplete excavation or underpinning operation. The owners can agree the security or, if they disagree, the appointed surveyors determine what is appropriate.

Who Pays the Costs?

The Building Owner normally pays the reasonable costs of the procedure where the work is solely for their benefit. Costs can be shared in other circumstances, including some repairs to a shared structure. The appointed surveyors determine the allocation, taking account of the work, the benefit to each owner and responsibility for any defect.

Frequently Asked Questions

Do I need an Award if my neighbour consents?

An initial Award is not normally needed where the adjoining owner gives valid written consent and no dispute exists. A condition record can still be arranged, and consent does not remove the owners’ rights and responsibilities under the Act if a disagreement arises later, for example over damage.

Is a Schedule of Condition compulsory?

The Act does not make a Schedule of Condition compulsory, but a record made before work starts gives both owners useful evidence if damage is reported later. We normally prepare one as part of a Party Wall surveyor appointment, concentrating on the areas the proposed work could affect.

How long is a Party Wall notice valid?

For Party Structure and excavation notices, the notified work must begin within 12 months of service and then proceed without undue delay. Line of Junction notices follow different provisions. If the programme is delayed or the design changes, send us the revised details so we can check whether fresh notices are needed.

Can a Party Wall Award be changed?

Send revised drawings to the appointed surveyors before carrying out any changed work. New notices or an additional Award may be needed where the proposals differ from those already covered. Further Awards can address later matters in dispute, but they are not a way to reopen the original decision instead of appealing it.

Can I appeal a Party Wall Award?

Either owner can appeal to the county court within 14 days, including the day the Award is served on them. If you are considering an appeal, seek legal advice promptly: discussing the Award with the surveyors or making a complaint does not extend that deadline.

What if work starts without a notice?

Surveyors cannot simply make a retrospective Award to regularise work carried out without a valid notice. We can review what has happened and advise on the surveying issues; a solicitor may be needed urgently if ongoing work must be stopped. Our guide explains what to do when work starts without a Party Wall notice.