Check What Is Missing

A missing completion certificate can mean that the paperwork has been lost, an application was never signed off, or the conversion was carried out without approval. Establish which applies before deciding how to proceed: if an application already exists, the Building Control body involved may be able to explain what remains outstanding.

Look for the application, approved drawings, structural calculations, inspection records and any completion or final certificate. The owner, previous owner or Building Control body may hold copies. Planning Permission deals with different matters and does not establish Building Regulations compliance; if you are buying, discuss the missing records with your solicitor before approaching Building Control.

What the Inspection Covers

We inspect the accessible roof structure, floors, beams and supports, together with the stairs, fire precautions, insulation and ventilation. The report explains visible defects, concerns about the conversion and the further checks needed to understand its construction.

Finishes can conceal important details, such as beam bearings, floor joists and insulation. A visual building survey cannot verify those details or certify compliance, but it can identify where the available records and visible construction leave questions to resolve.

Architectural section through a house with roof-space accommodation and rear extension
Proposed building section showing roof-space accommodation, floor levels and the stair.

Further Investigation & Structural Advice

Altered roof trusses, movement, inadequate supports or missing calculations may call for a structural assessment. Where the inspection identifies these concerns, we can coordinate advice from our consulting Chartered Structural Engineer and explain which concealed details may need to be exposed, with the owner’s permission, before an opinion can be given.

The Regularisation Route

For an unauthorised house conversion carried out on or after 11 November 1985, the local authority may consider a regularisation application. It assesses the work against the requirements that applied when it was carried out and may need drawings, calculations, testing, opening-up or remedial work before deciding whether it can issue a certificate.

A survey helps identify the likely building issues, but the local authority determines what evidence and work it needs. Our Building Regulations regularisation service explains how we can assist with drawings, supporting information and the response to Building Control.

Buying or Selling the Property

Allow time for the missing records and any construction concerns to be investigated before committing to the purchase. Your solicitor can advise on the legal and lender requirements, while the survey and any further assessment explain the physical condition and likely work needed.

If you are selling, gathering the available records early can help you answer the buyer’s enquiries. An indemnity policy does not establish that the conversion is safely constructed or that its defects have been put right.

Frequently Asked Questions

Can a surveyor issue the missing completion certificate?

A survey report cannot replace a Building Control certificate. The relevant Building Control body deals with completion of an existing application; a regularisation application for an ordinary house conversion is made to the local authority.

Will indemnity insurance prove the conversion is safe?

Indemnity insurance covers the risks specified in the policy and does not assess the construction, fire precautions or structure. Ask your solicitor what the proposed policy covers and use the inspection findings to understand any building concerns.

Will the survey need opening-up?

The initial inspection is visual. If a concealed beam, support or floor detail needs further examination, we explain the reason and the access required so targeted investigation can be arranged with the owner’s permission.

Can you inspect the whole house as well?

Yes. We can inspect the property through a Full Building Survey (Level 3), with particular attention to the loft conversion and any concerns you raise. Tell us about missing records before booking so we can explain what the survey covers and whether a separate investigation is needed.